Emergency level and enablers | AHP rank | BWM rank |
---|
Particularly significant issues |
Solid particles emission | 1 | 1 |
Reliability | 2 | 2 |
Production rate | 3 | 4 |
Production cost | 4 | 3 |
On-site safety | 5 | 5 |
Electricity demand fulfilment | 6 | 6 |
Noxious gas emission | 7 | 8 |
Energy efficiency | 8 | 7 |
Important issues |
Occupied land | 9 | 9 |
Worker health | 10 | 10 |
Transmission loss | 11 | 11 |
Maturity | 12 | 12 |
Soil pollution | 13 | 13 |
Establishment cost | 14 | 14 |
Non-urgent issues |
Upgradeability | 15 | 16 |
National supply control | 16 | 15 |
Number of talents | 17 | 17 |
Water pollution | 18 | 19 |
Required employer | 19 | 18 |
Market share | 20 | 20 |