Table 2 Example cluster for calculating the average additional costs of upgrading compared to pure biogas production

From: A consolidated potential analysis of bio-methane and e-methane using two different methods for a medium-term renewable gas supply in Germany

Cluster Power [kW] Plants Pipe length "web" [m] Pipe length “web” × 1.44 [m] Pipe length "star" [m]
A 8739 13 32,835 47,282 76,307
B 6635 10 41,643 59,966 80,196
C 9210 14 39,592 57,012 86,939
D 5321 10 30,881 44,469 66,336
E 15,591 19 45,989 66,224 113,180
F 8703 12 31,252 45,003 52,609
G 15,930 26 69,337 99,845 159,141
H 11,874 20 52,900 76,176 135,942
I 8645 14 35,344 50,895 71,157
J 18,643 33 63,188 90,991 208,173
K 5654 8 22,719 32,715 36,453
Ø 10,450 16 42,335 60,962 98,767