Table 6 Scenario description

From: Competing for space? A multi-criteria scenario framework intended to model the energy–biodiversity–land nexus for regional renewable energy planning based on a German case study

 

Scenario title

No.

Business as usual (BAU) planning for wind energy

Wind energy under planning practice and 100% in bird priority zones (BAU)

Wind energy planning is based on the draft regional plan 3.0 for the Havelland-Fläming region, using the current planning concept [73, 119]. Wind energy is developed in modeled bird priority zones as there is no bird priority zone concept in Brandenburg

#1A

Ground-mounted PV on subsidized areas and 100% in bird priority zones (BAU)

Ground-mounted PV is being developed on potential, subsidized areasa (‘EEG-areas’). PV is developed in bird priority zones as there is no bird priority zone concept in Brandenburg

#2A

Agri-PV on agricultural areas (soil ranking number < 23) and 100% in bird priority zones (BAU)

Agri-PV is developed on agricultural areas with a soil number less than 23, i.e., lower-yielding land [109]. Agri-PV systems are located in bird priority zones as there is no bird priority zone concept in Brandenburg

#3A

Planning variants in bird priority zones

Wind energy in bird priority zones

To a small extent, wind turbines are allowed to be installed in bird priority zones as is the case in federal states Bavaria, or Hesse. Other federal states exclude wind turbines from being installed in bird priority zones to ensure that bird priority zones can fulfill their function of protecting populations, such as in Saxony Anhalt [74]. Large-scale wind energy development would contradict the species protection objectives of the bird priority zones. Therefore, it is assumed that 0%, 5% and 10% of the area could be used for wind energy development

#4A-D

A-0%

B-5%

C-10%

D-Wind energy areas

Repowering in bird priority zones

Dealing with existing turbines in new bird priority zone approaches calls for planning visualization to determine the extent to which repowering can occur. Due to the larger turbine dimensions, a higher capacity can be expected [125]. At the same time, changes in species protection and noise legislation may mean that the same capacity cannot be achieved on the site [172]. Existing turbines are considered older when they were built after 2005 and are 18 years or older. It is therefore assumed that the same capacity could be realized by repowering in bird priority zones (1:1). Alternatively, it is assumed that double the capacity could be realized (2:1). The additional capacity is added to the region’s development potential for wind energy

#5A-B

A-100%

B-200%

Retrofitting in bird priority zones

As an alternative to repowering, existing facilities in bird priority zones could be retrofitted, i.e., modernized [127]. A partial retrofit of 50% is considered possible if existing turbines are operated beyond the age of 20 years

#6A

A-50%

View full size image

Bird priority zones and efficient areas for wind energy

Bird priority zones can lead to spatial trade-offs with planning parameters that aim to optimize the energy efficiency of wind energy planning [173, 174]. Bird priority zones may also provide good habitat quality for species in areas where wind speeds are particularly favorable for wind turbines ([175], cf. [174]). It is varied how the area impact for wind energy would change if the windiest sites in bird priority zones were used for wind energy at 10% and 5% when the wind speed is greater than 5.5 m/s [119]

#7A-B

A-10%

B-5%

View full size image

Bird priority zones and higher electricity demand

Bird priority zones can also be located in areas where there is a higher demand for electricity in the vicinity of settlements. Ideally, it would be sensible to locate wind turbines where there are electricity consumers [176]. It is examined how the area impact for wind energy changes when turbines are installed in bird priority zones near residential areas. A buffer of 800 m is assumed to ensure noise protection distances [119]. To ensure proximity to settlements, it is also considered that wind energy can be installed in bird priority zones within a 1 km strip

#8A

A-1 km strip

View full size image

Bird priority zones and network efficiency

Planning for wind energy would be (cost-)efficient if turbines were located near grid feed-in points, such as transformer stations [173, 174]. These areas may also overlap with bird priority zones. Therefore, it is assumed that wind turbines can be located in bird priority zones if they are less than 5 km from 110 kV substations

#9A

A- < 5 km

Photovoltaics and planning variants in bird priority zones

Ground-mounted PV in bird priority zones

With regard to the share of renewable energy in the energy mix, the extent is examined to which PV can be developed in the region under bird priority zone approaches. Since PV may have a lower spatial trade-off potential in terms of collisions with avifauna compared to wind energy [177,178,179], a proportionally smaller development in bird priority zones would be possible (0%, 10%, 20%). Habitats could be established, which allows structural richness for species through additional measures [180]

#10A

A-0%

B-10%

C-20%

Vertical PV in bird priority zones

Vertical PV systems can capture sunlight from both east and west [107]. It is assumed that, to a small extent, vertical PV could be installed in areas of bird priority zones. Their characteristics could further reduce trade-offs with birds, especially if the area under the module lines were to be heavily farmed, and now providing a potential habitat for small mammals, such as mouse, for raptors to hunt. The power density per module is lower than for ground-mounted PV [108]. It is assumed that vertical PV could be installed on a small scale in bird priority zones (0%, 10%, 20%)

#11A-C

A-5%

B-10%

C-20%

Agri-PV in bird priority zones

Agri-PV is typically a higher elevation PV system that allows for the cultivation of agricultural crops, such as berries [164, 181, 182]. To minimize the impact on land for food production, it is assumed that agri-PV would be developed on agricultural land with soil rating number of less than 23 [109]. These areas have a lower yield expectation. Therefore, the potential loss of agricultural products such as corn and wheat, which cannot be easily grown under PV modules, is not expected to be too significant. Small thresholds of 0%, 10%, and 20% are assumed to determine whether areas in bird priority zones would also need to be developed with agri-PV to meet energy targets

#12A-C

A-0%

B-10%

C-20%

View full size image

Energy mix of ground-mounted PV and wind energy in bird priority zones

The concern is whether wind energy and PV together would be necessary in bird priority zones to meet the area and energy targets. To fulfill the conservation mandate of bird priority zones for populations and to resolve species protection conflicts, this can only be a small part. Therefore, for both energy sources, it is assumed that only a lower share of 10% would allow development in bird priority zones

#13A

A-10%

Ground-mounted PV to substitute for missing wind energy according to achieved targets with BAU

The energy mix of renewable energies is addressed, whether, alternatively, sufficient area would be available to additionally cover the deficit with PV, which cannot be achieved with wind energy in BAU of regional planning. In addition to the PV potential that would be required to meet the energy targets for PV, the substitution of energy quantities with PV would have to be realized. To this end, an analysis is made of what the area impact would be if ground-mounted PV were not installed in bird priority zones

#14A

A-0%

Planning variants of criteria requiring area with fixed bird priority zones

Bird priority zones and no species-specific buffers

In addition to bird priority zones, there are other land use interests that can take up a larger share of the area. Species-specific buffers, designed to ensure species protection in the permitting process, can account for a significant share of the area [75, 128]. To measure the amount of land left for wind energy if only bird priority zones were used as a planning criterion, the planning for wind turbines without species-specific buffers is shown

#15A

A-no species-specific buffers

Bird priority zones and varying buffer to settlements

Settlement buffers exceeding the federal emission protection buffers are often imposed by decision-makers to secure the acceptance of wind energy by local residents [128]. The BAU scenario assumes a buffer of about 1000 m to residential areas. However, research on acceptance suggests that buffers have little effect on the acceptance of wind energy [183]. It is examined how the area impact for wind energy changes when planning exclusively with the 800 m setback based on emission law

#16A

A-800 m

Bird priority zones and forests

Brandenburg is rich in woodlands [184]. The development of wind energy in forests is controversial due to possible impacts on birds and bats, also for the economic use of the forest [185, 186]. As forest areas make up a larger part of the region, thresholds are examined in terms of their target footprint if wind turbines are additionally installed in forest areas to a certain extent (2%, 4%). The installation of wind energy in deciduous forests is potentially more conflictual than in coniferous forests. Therefore, only coniferous forests are considered

#17A-B

A-4%

B-2%

Bird priority zones and landscape protection areas

Landscape protection areas are intended to preserve the general character of the landscape, also for recreation and tourismb. In BAU, landscape protection areas are open to balancing, but have been excluded in the current draft regional plan [119]. Regulations at the federal level envisage opening up landscape protection areas for wind turbines to achieve the spatial targets [187, 188]. Thresholds in this scenario aim to open a small percentage (1%, 3%) of landscape protection areas for wind energy

#18A-B

A-3%

B-1%

Bird priority zones and nature park areas

Nature parks are protected, often large landscape areas that have been created through long forms of landscape managementc. However, they usually combine several other categories of protection. Due to the larger scale of nature parks, the extent to which additional development of wind energy in nature parks can lead to the achievement of spatial targets is examined

#19A-B

A-4%

B-2%

Bird priority zones and open spaces

The free space network includes those parts of the open space that are of high regional value, and that are connected to each other [73, 119]. Due to its large size, this planning category is examined to determine how small-scale wind energy development in areas for open spaces could lead to the achievement of spatial targets

#20A-B

A-4%

B-2%

  1. a§37 (1) Renewable Energy Act (EEG 2023)
  2. b§26 (1) Federal Nature Conservation Act (BNatSchG)
  3. c§27 (1) Federal Nature Conservation Act (BNatSchG)